Daily summary The day's site activity focused on Plastering work, Concrete casting work, and Lantai Granit across 16 work areas, supported by Skim coat work, Pembersihan Area Kerja, and Work item needs review.
Work by area Work area 01 · page 1 of 3 Unit C Third Floor
Standard area
Unit C Third Floor 4 entries on this page Concrete casting work Lantai Granit
Affan Akseh Anang Andri Awang Fatta Fian Huri Pak Farel Ropek Zaeni rizal
Concrete casting work Affan Unit C Third Floor
Concrete casting work Akseh Unit C Third Floor
Lantai Granit Anang Unit C Third Floor
Lantai Granit Andri Unit C Third Floor
Work by area Work area 01 · page 2 of 3 Unit C Third Floor
Standard area
Unit C Third Floor 4 entries on this page Concrete casting work Awang Unit C Third Floor
Work by area Work area 01 · page 3 of 3 Unit C Third Floor
Standard area
Unit C Third Floor 4 entries on this page Concrete casting work Pak Farel Unit C Third Floor
Work by area Work area 02 · page 1 of 2 Unit A facade
Standard area
Unit A facade 4 entries on this page Plastering work
Bambang Dhoni Fery Hosnan Miskat Yayan
Plastering work Bambang Unit A facade
Work by area Work area 02 · page 2 of 2 Unit A facade
Standard area
Unit A facade 2 entries on this page Plastering work Miskat Unit A facade
Work by area Work area 03 · page 1 of 2 Unit B Third Floor
Standard area
Unit B Third Floor 4 entries on this page Lantai Granit Plastering work Skim coat work
Afis Al Ari Imron Toni Wahid
Skim coat work Afis Unit B Third Floor
Work by area Work area 03 · page 2 of 2 Unit B Third Floor
Standard area
Unit B Third Floor 2 entries on this page Plastering work Toni Unit B Third Floor
Work by area Work area 04 Unit A Room 29
Standard area
Unit A Room 29 3 entries on this page Pembersihan Area Kerja Plastering work
Munir Yusuf Zaini A
Pembersihan Area Kerja Munir Unit A Room 29
Work by area Work area 05 Unit A lobi
Standard area
Unit A lobi 3 entries on this page Concrete casting work Lightweight brick installation Plastering work
Adip Riswan Wafi
Lightweight brick installation Adip Unit A lobi
Work by area Work area 06 Unit B tangga belakang
Standard area
Unit B tangga belakang 3 entries on this page Lantai Granit Plastering work
Dofir Hanan Tormudi
Lantai Granit Dofir Unit B tangga belakang
Work by area Work area 07 Building C · Rooftop Floor
Standard area
Building C · Rooftop Floor 2 entries on this page Pembersihan Area Kerja
Rian suarji
Pembersihan Area Kerja Rian Building C · Rooftop Floor
Work by area Work area 08 Unit B facade
Standard area
Unit B facade 2 entries on this page Skim coat work
Halim Wahyu
Skim coat work Halim Unit B facade
Work by area Work area 09 Unit C Room 14
Standard area
Unit C Room 14 2 entries on this page Work item needs review
Hakik Soleh
Work item needs review Hakik Unit C Room 14
Work by area Work area 10 Area not filled
Standard area
Area not filled 1 entry on this page Belanja / Logistik Site
Faisal
Belanja / Logistik Site Faisal Area not filled
Work by area Work area 11 Kolam pagar air mancur
Standard area
Kolam pagar air mancur 1 entry on this page Plastering work
Gazali
Plastering work Gazali Kolam pagar air mancur
Work by area Work area 12 Unit A Room 20
Standard area
Unit A Room 20 1 entry on this page Natural stone installation
Muhammad
Natural stone installation Muhammad Unit A Room 20
Work by area Work area 13 Unit A lobi Second Floor
Standard area
Unit A lobi Second Floor 1 entry on this page Lightweight brick installation
Topik
Lightweight brick installation Topik Unit A lobi Second Floor
Work by area Work area 14 Unit C basement
Standard area
Unit C basement 1 entry on this page Skim coat work
Pranata
Skim coat work Pranata Unit C basement
Work by area Work area 15 Unit C kaca office
Standard area
Unit C kaca office 1 entry on this page Pembersihan Area Kerja
Dulbari
Pembersihan Area Kerja Dulbari Unit C kaca office
Work by area Work area 16 Unit C samping basement
Standard area
Unit C samping basement 1 entry on this page Work item needs review
Subawi
Work item needs review Subawi Unit C samping basement
Standard check and completeness Work item does not match standard naming yet 3 entries The field description does not match project knowledge or BOQ/RAB finance records strongly enough yet.
Area belum diisi 1 entry Lokasi belum ditulis oleh team lapangan.
Area does not meet report standards yet 1 entry The site input does not mention a work area, so it is not used as a final progress conclusion by area.