Daily summary The day's site activity focused on Plastering work, Work item needs review, and Lantai Granit across 22 work areas, supported by Skim coat work, Lightweight brick installation, and Pembersihan Area Kerja.
Work by area Work area 01 · page 1 of 2 Unit A facade
Standard area
Unit A facade 4 entries on this page Plastering work
Bambang Fery Hosnan Miskat Yayan
Plastering work Bambang Unit A facade
Plastering work Fery Unit A facade
Plastering work Hosnan Unit A facade
Plastering work Miskat Unit A facade
Work by area Work area 01 · page 2 of 2 Unit A facade
Standard area
Unit A facade 1 entry on this page Plastering work Yayan Unit A facade
Work by area Work area 02 · page 1 of 2 Unit B Third Floor
Standard area
Unit B Third Floor 4 entries on this page Lantai Granit Plastering work
Andri Ari Imron Sam Tormudi
Lantai Granit Andri Unit B Third Floor
Work by area Work area 02 · page 2 of 2 Unit B Third Floor
Standard area
Unit B Third Floor 1 entry on this page Plastering work Tormudi Unit B Third Floor
Work by area Work area 03 Kolam pagar air mancur
Standard area
Kolam pagar air mancur 4 entries on this page Plastering work
Afis Gazali Hakik Zaeni
Plastering work Afis Kolam pagar air mancur
Work by area Work area 04 Unit A lobi
Standard area
Unit A lobi 4 entries on this page Lightweight brick installation Work item needs review
Al Fian Yusuf rizal
Work item needs review Al Unit A lobi
Work by area Work area 05 Unit A lobi Second Floor
Standard area
Unit A lobi Second Floor 4 entries on this page Lightweight brick installation Plastering work
Adip Muzaki Riswan Topik
Lightweight brick installation Adip Unit A lobi Second Floor
Work by area Work area 06 Building C · Rooftop Floor
Standard area
Building C · Rooftop Floor 3 entries on this page Lantai Granit Pembersihan Area Kerja
Hoirul Rian suarji
Pembersihan Area Kerja Hoirul Building C · Rooftop Floor
Work by area Work area 07 Unit B Room 17
Standard area
Unit B Room 17 3 entries on this page Chipping work Natural stone installation Pembersihan Area Kerja
Dulbari Munir Pak Farel
Chipping work Dulbari Unit B Room 17
Work by area Work area 08 Unit B Second Floor
Standard area
Unit B Second Floor 3 entries on this page Plastering work Skim coat work
Dhoni Halim Naim
Skim coat work Dhoni Unit B Second Floor
Work by area Work area 09 Unit C basement
Standard area
Unit C basement 3 entries on this page Rebar work Skim coat work
Akseh Huri Pranata
Rebar work Akseh Unit C basement
Work by area Work area 10 Unit C Room 14
Standard area
Unit C Room 14 3 entries on this page Tile installation Work item needs review
Anang Pawait Soleh
Tile installation Anang Unit C Room 14
Work by area Work area 11 Unit A
Standard area
Unit A 2 entries on this page Work item needs review
Fatta Wafi
Work item needs review Fatta Unit A
Work by area Work area 12 Unit A rooftop
Standard area
Unit A rooftop 2 entries on this page Plastering work
Affan Awang
Plastering work Affan Unit A rooftop
Work by area Work area 13 Unit B facade
Standard area
Unit B facade 2 entries on this page Skim coat work
Ridho Toni
Skim coat work Ridho Unit B facade
Work by area Work area 14 Unit B tangga belakang
Standard area
Unit B tangga belakang 2 entries on this page Lantai Granit
Dofir Hanan
Lantai Granit Dofir Unit B tangga belakang
Work by area Work area 15 Area not filled
Standard area
Area not filled 1 entry on this page Belanja / Logistik Site
Faisal
Belanja / Logistik Site Faisal Area not filled
Work by area Work area 16 Unit A Room 29
Standard area
Unit A Room 29 1 entry on this page Lightweight brick installation
Zaini A
Lightweight brick installation Zaini A Unit A Room 29
Work by area Work area 17 Unit A lobi rooftop
Standard area
Unit A lobi rooftop 1 entry on this page Work item needs review
Ropek
Work item needs review Ropek Unit A lobi rooftop
Work by area Work area 18 Unit B facade Second Floor
Standard area
Unit B facade Second Floor 1 entry on this page Skim coat work
Wahyu
Skim coat work Wahyu Unit B facade Second Floor
Work by area Work area 19 Unit B facade Third Floor
Standard area
Unit B facade Third Floor 1 entry on this page Skim coat work
Wahid
Skim coat work Wahid Unit B facade Third Floor
Work by area Work area 20 Unit C
Standard area
Unit C 1 entry on this page Pembersihan Area Kerja
Subawi
Pembersihan Area Kerja Subawi Unit C
Work by area Work area 21 Unit C Room 20
Standard area
Unit C Room 20 1 entry on this page Natural stone installation
Muhammad
Natural stone installation Muhammad Unit C Room 20
Work by area Work area 22 Unit C Room 25
Standard area
Unit C Room 25 1 entry on this page Tile installation
Bais
Tile installation Bais Unit C Room 25
Standard check and completeness Work item does not match standard naming yet 8 entries The field description does not match project knowledge or BOQ/RAB finance records strongly enough yet.
Area belum diisi 1 entry Lokasi belum ditulis oleh team lapangan.
Area does not meet report standards yet 1 entry The site input does not mention a work area, so it is not used as a final progress conclusion by area.