The day's site activity focused on Lantai Granit, Work item needs review, and Skim coat work across 23 work areas, supported by Pembersihan Area Kerja, Plastering work, and Lightweight brick installation.
Work by area
Work area 01Building C · Rooftop Floor
Standard area
Building C · Rooftop Floor
4 entries on this page
Lantai GranitSkim coat work
BaisRianRiswanTormudi
Lantai GranitBais
Building C · Rooftop Floor
Lantai GranitRian
Building C · Rooftop Floor
Skim coat workRiswan
Building C · Rooftop Floor
Skim coat workTormudi
Building C · Rooftop Floor
Work by area
Work area 02Unit A facade
Standard area
Unit A facade
3 entries on this page
Work item needs review
HuriToniWahid
Work item needs reviewHuri
Unit A facade
Work by area
Work area 03Unit A Room 19
Standard area
Unit A Room 19
3 entries on this page
Lightweight brick installationPembersihan Area Kerja
DulbariMuhammadRopek
Lightweight brick installationDulbari
Unit A Room 19
Work by area
Work area 04Unit B kolam
Standard area
Unit B kolam
3 entries on this page
Work item needs review
FattaFianWafi
Work item needs reviewFatta
Unit B kolam
Work by area
Work area 05Unit C Room 23
Standard area
Unit C Room 23
3 entries on this page
Lantai GranitSkim coat work
AndriDaniGani
Lantai GranitAndri
Unit C Room 23
Work by area
Work area 06Unit A Second Floor
Standard area
Unit A Second Floor
2 entries on this page
Skim coat work
MiskatYayan
Skim coat workMiskat
Unit A Second Floor
Work by area
Work area 07Unit A lobi
Standard area
Unit A lobi
2 entries on this page
Plastering work
CiptoMistun
Plastering workCipto
Unit A lobi
Work by area
Work area 08Unit C Room 14
Standard area
Unit C Room 14
2 entries on this page
Work item needs review
HakikPawait
Work item needs reviewHakik
Unit C Room 14
Work by area
Work area 09Unit C kolam ikan
Standard area
Unit C kolam ikan
2 entries on this page
Plastering workWork item needs review
SyaifulTopik
Work item needs reviewSyaiful
Unit C kolam ikan
Work by area
Work area 10Unit C Third Floor
Standard area
Unit C Third Floor
2 entries on this page
Cor Plat LantaiSkim coat work
HoirulZaeni
Skim coat workHoirul
Unit C Third Floor
Work by area
Work area 11Unit C tangga ujung
Standard area
Unit C tangga ujung
2 entries on this page
Lantai Granit
Abdullah Wiwin
Lantai GranitAbdullah
Unit C tangga ujung
Work by area
Work area 12Area basement
Standard area
Area basement
1 entry on this page
Pembersihan Area Kerja
Subawi
Pembersihan Area KerjaSubawi
Area basement
Work by area
Work area 13Area not filled
Standard area
Area not filled
1 entry on this page
Belanja / Logistik Site
Faisal
Belanja / Logistik SiteFaisal
Area not filled
Work by area
Work area 14Area proyek
Standard area
Area proyek
1 entry on this page
Pembersihan Area Kerja
Pak Farel
Pembersihan Area KerjaPak Farel
Area proyek
Work by area
Work area 15Unit A tangga Second Floor
Standard area
Unit A tangga Second Floor
1 entry on this page
Skim coat work
Hosnan
Skim coat workHosnan
Unit A tangga Second Floor
Work by area
Work area 16Unit B Second Floor
Standard area
Unit B Second Floor
1 entry on this page
Lantai Granit
Dofir
Lantai GranitDofir
Unit B Second Floor
Work by area
Work area 17Unit B tangga Second Floor
Standard area
Unit B tangga Second Floor
1 entry on this page
Lantai Granit
Adip
Lantai GranitAdip
Unit B tangga Second Floor
Work by area
Work area 18Unit C Room 22
Standard area
Unit C Room 22
1 entry on this page
Lantai Granit
Ari
Lantai GranitAri
Unit C Room 22
Work by area
Work area 19Unit C Room 24
Standard area
Unit C Room 24
1 entry on this page
Work item needs review
suarji
Work item needs reviewsuarji
Unit C Room 24
Work by area
Work area 20Unit C tangg ke office
Standard area
Unit C tangg ke office
1 entry on this page
Lantai Granit
Roni
Lantai GranitRoni
Unit C tangg ke office
Work by area
Work area 21Unit C tangga Room 15
Standard area
Unit C tangga Room 15
1 entry on this page
Tile installation
Affan
Tile installationAffan
Unit C tangga Room 15
Work by area
Work area 22Unit C tangga Room 25
Standard area
Unit C tangga Room 25
1 entry on this page
Pembersihan Area Kerja
Munir
Pembersihan Area KerjaMunir
Unit C tangga Room 25
Work by area
Work area 23Unit C tangga ke office
Standard area
Unit C tangga ke office
1 entry on this page
Lantai Granit
Sei
Lantai GranitSei
Unit C tangga ke office
Standard check and completeness
Work item does not match standard naming yet10 entries
The field description does not match project knowledge or BOQ/RAB finance records strongly enough yet.
Area belum diisi1 entry
Lokasi belum ditulis oleh team lapangan.
Area does not meet report standards yet1 entry
The site input does not mention a work area, so it is not used as a final progress conclusion by area.