The day's site activity focused on Lantai Granit, Plastering work, and Work item needs review across 23 work areas, supported by Skim coat work, Cor Plat Lantai, and Pembersihan Area Kerja.
Work by area
Work area 01 · page 1 of 3Unit A lobi
Standard area
Unit A lobi
4 entries on this page
Cor Plat LantaiLightweight brick installationPlastering workRebar work
AksehAwangCiptoDulbariHuriMistunToniWahidrizal
Rebar workAkseh
Unit A lobi
Cor Plat LantaiAwang
Unit A lobi
Plastering workCipto
Unit A lobi
Plastering workDulbari
Unit A lobi
Work by area
Work area 01 · page 2 of 3Unit A lobi
Standard area
Unit A lobi
4 entries on this page
Cor Plat LantaiHuri
Unit A lobi
Work by area
Work area 01 · page 3 of 3Unit A lobi
Standard area
Unit A lobi
1 entry on this page
Rebar workrizal
Unit A lobi
Work by area
Work area 02 · page 1 of 2Unit B kolam
Standard area
Unit B kolam
4 entries on this page
Work item needs review
AffanFattaFianRivalWafi
Work item needs reviewAffan
Unit B kolam
Work by area
Work area 02 · page 2 of 2Unit B kolam
Standard area
Unit B kolam
1 entry on this page
Work item needs reviewWafi
Unit B kolam
Work by area
Work area 03Building C · Rooftop Floor
Standard area
Building C · Rooftop Floor
4 entries on this page
Lantai GranitPlastering work
BaisRianRiswanTormudi
Lantai GranitBais
Building C · Rooftop Floor
Work by area
Work area 04Unit C tangga ujung
Standard area
Unit C tangga ujung
4 entries on this page
Lantai GranitPlastering work
Abdullah MuzakiWiwinYusuf
Lantai GranitAbdullah
Unit C tangga ujung
Work by area
Work area 05Unit C Room 22
Standard area
Unit C Room 22
3 entries on this page
Lantai GranitPembersihan Area Kerja
AlAriMuhammad
Lantai GranitAl
Unit C Room 22
Work by area
Work area 06Unit C kolam ikan
Standard area
Unit C kolam ikan
3 entries on this page
Plastering work
BambangFeryRahul
Plastering workBambang
Unit C kolam ikan
Work by area
Work area 07Unit A belakang
Standard area
Unit A belakang
2 entries on this page
Skim coat work
HosnanYayan
Skim coat workHosnan
Unit A belakang
Work by area
Work area 08Unit B Second Floor
Standard area
Unit B Second Floor
2 entries on this page
Lantai Granit
AdipDofir
Lantai GranitAdip
Unit B Second Floor
Work by area
Work area 09Unit C basement
Standard area
Unit C basement
2 entries on this page
Pembersihan Area KerjaRebar work
SubawiZaeni
Pembersihan Area KerjaSubawi
Unit C basement
Work by area
Work area 10Unit C tangga ke office
Standard area
Unit C tangga ke office
2 entries on this page
Lantai Granit
RoniSei
Lantai GranitRoni
Unit C tangga ke office
Work by area
Work area 11Area not filled
Standard area
Area not filled
1 entry on this page
Belanja / Logistik Site
Faisal
Belanja / Logistik SiteFaisal
Area not filled
Work by area
Work area 12Unit A belakang Second Floor
Standard area
Unit A belakang Second Floor
1 entry on this page
Skim coat work
Miskat
Skim coat workMiskat
Unit A belakang Second Floor
Work by area
Work area 13Unit A Room 29
Standard area
Unit A Room 29
1 entry on this page
Work item needs review
suarji
Work item needs reviewsuarji
Unit A Room 29
Work by area
Work area 14Unit A samping lobi
Standard area
Unit A samping lobi
1 entry on this page
Ground leveling work
Hakik
Ground leveling workHakik
Unit A samping lobi
Work by area
Work area 15Unit AC tangga Room 25
Standard area
Unit AC tangga Room 25
1 entry on this page
Lantai Granit
Sam
Lantai GranitSam
Unit AC tangga Room 25
Work by area
Work area 16Unit B
Standard area
Unit B
1 entry on this page
Pembersihan Area Kerja
Pak Farel
Pembersihan Area KerjaPak Farel
Unit B
Work by area
Work area 17Unit B belakang
Standard area
Unit B belakang
1 entry on this page
Skim coat work
Topik
Skim coat workTopik
Unit B belakang
Work by area
Work area 18Unit B Room 27
Standard area
Unit B Room 27
1 entry on this page
Lantai Granit
Dani
Lantai GranitDani
Unit B Room 27
Work by area
Work area 19Unit B Third Floor
Standard area
Unit B Third Floor
1 entry on this page
Plastering work
Ropek
Plastering workRopek
Unit B Third Floor
Work by area
Work area 20Unit C Room 14
Standard area
Unit C Room 14
1 entry on this page
Work item needs review
Pawait
Work item needs reviewPawait
Unit C Room 14
Work by area
Work area 21Unit C Third Floor
Standard area
Unit C Third Floor
1 entry on this page
Skim coat work
Hoirul
Skim coat workHoirul
Unit C Third Floor
Work by area
Work area 22Unit C tangga basement
Standard area
Unit C tangga basement
1 entry on this page
Skim coat work
Pranata
Skim coat workPranata
Unit C tangga basement
Work by area
Work area 23Unit C tangga Room 25
Standard area
Unit C tangga Room 25
1 entry on this page
Lantai Granit
Andri
Lantai GranitAndri
Unit C tangga Room 25
Standard check and completeness
Work item does not match standard naming yet7 entries
The field description does not match project knowledge or BOQ/RAB finance records strongly enough yet.
Area belum diisi1 entry
Lokasi belum ditulis oleh team lapangan.
Area does not meet report standards yet1 entry
The site input does not mention a work area, so it is not used as a final progress conclusion by area.