The day's site activity focused on Lantai Granit, Plastering work, and Work item needs review across 20 work areas, supported by Cor Plat Lantai, Skim coat work, and Lightweight brick installation.
Work by area
Work area 01 · page 1 of 2Unit A lobi
Standard area
Unit A lobi
4 entries on this page
Cor Plat LantaiLightweight brick installation
AksehAwangCiptoMistunRiswanToniWahidZaeni
Cor Plat LantaiAkseh
Unit A lobi
Cor Plat LantaiAwang
Unit A lobi
Lightweight brick installationCipto
Unit A lobi
Lightweight brick installationMistun
Unit A lobi
Work by area
Work area 01 · page 2 of 2Unit A lobi
Standard area
Unit A lobi
4 entries on this page
Cor Plat LantaiRiswan
Unit A lobi
Work by area
Work area 02 · page 1 of 2Unit A
Standard area
Unit A
4 entries on this page
Plastering workWork item needs review
AffanFattaFianRidhoWafi
Work item needs reviewAffan
Unit A
Work by area
Work area 02 · page 2 of 2Unit A
Standard area
Unit A
1 entry on this page
Work item needs reviewWafi
Unit A
Work by area
Work area 03Unit C basement
Standard area
Unit C basement
4 entries on this page
Pembersihan Area KerjaRebar work
HuriPak FarelSubawirizal
Rebar workHuri
Unit C basement
Work by area
Work area 04Unit C kolam ikan
Standard area
Unit C kolam ikan
4 entries on this page
Plastering work
BambangFeryRahulRival
Plastering workBambang
Unit C kolam ikan
Work by area
Work area 05Unit C tangga ujung
Standard area
Unit C tangga ujung
4 entries on this page
Lantai GranitPlastering work
Abdullah MuzakiWiwinYusuf
Lantai GranitAbdullah
Unit C tangga ujung
Work by area
Work area 06Unit A Second Floor
Standard area
Unit A Second Floor
3 entries on this page
Skim coat work
HosnanMiskatYayan
Skim coat workHosnan
Unit A Second Floor
Work by area
Work area 07Unit C Room 22
Standard area
Unit C Room 22
3 entries on this page
Lantai GranitPembersihan Area Kerja
AlAriMuhammad
Lantai GranitAl
Unit C Room 22
Work by area
Work area 08Unit B belakang
Standard area
Unit B belakang
2 entries on this page
Plastering work
HakikTopik
Plastering workHakik
Unit B belakang
Work by area
Work area 09Unit B Third Floor
Standard area
Unit B Third Floor
2 entries on this page
Lightweight brick installation
DulbariRopek
Lightweight brick installationDulbari
Unit B Third Floor
Work by area
Work area 10Unit B tangga Second Floor
Standard area
Unit B tangga Second Floor
2 entries on this page
Lantai Granit
AdipDofir
Lantai GranitAdip
Unit B tangga Second Floor
Work by area
Work area 11Unit C Room 25
Standard area
Unit C Room 25
2 entries on this page
Lantai GranitWork item needs review
Riansuarji
Lantai GranitRian
Unit C Room 25
Work by area
Work area 12Unit C tangga
Standard area
Unit C tangga
2 entries on this page
Lantai Granit
RoniSei
Lantai GranitRoni
Unit C tangga
Work by area
Work area 13Unit C tangga Room 25
Standard area
Unit C tangga Room 25
2 entries on this page
Lantai Granit
AndriSam
Lantai GranitAndri
Unit C tangga Room 25
Work by area
Work area 14Area not filled
Standard area
Area not filled
1 entry on this page
Belanja / Logistik Site
Faisal
Belanja / Logistik SiteFaisal
Area not filled
Work by area
Work area 15Unit B Room 17
Standard area
Unit B Room 17
1 entry on this page
Work item needs review
Hoirul
Work item needs reviewHoirul
Unit B Room 17
Work by area
Work area 16Unit C
Standard area
Unit C
1 entry on this page
Lantai Granit
Bais
Lantai GranitBais
Unit C
Work by area
Work area 17Unit C Room 14
Standard area
Unit C Room 14
1 entry on this page
Work item needs review
Pawait
Work item needs reviewPawait
Unit C Room 14
Work by area
Work area 18Unit C Room 26
Standard area
Unit C Room 26
1 entry on this page
Lantai Granit
Dani
Lantai GranitDani
Unit C Room 26
Work by area
Work area 19Unit C Third Floor
Standard area
Unit C Third Floor
1 entry on this page
Skim coat work
Tormudi
Skim coat workTormudi
Unit C Third Floor
Work by area
Work area 20Unit C tangga basement
Standard area
Unit C tangga basement
1 entry on this page
Skim coat work
Pranata
Skim coat workPranata
Unit C tangga basement
Standard check and completeness
Work item does not match standard naming yet7 entries
The field description does not match project knowledge or BOQ/RAB finance records strongly enough yet.
Area belum diisi1 entry
Lokasi belum ditulis oleh team lapangan.
Area does not meet report standards yet1 entry
The site input does not mention a work area, so it is not used as a final progress conclusion by area.