The day's site activity focused on Lantai Granit, Plastering work, and Work item needs review across 21 work areas, supported by Skim coat work, Pembersihan Area Kerja, and Cor Plat Lantai.
Work by area
Work area 01 · page 1 of 2Unit A lobi
Standard area
Unit A lobi
4 entries on this page
Cor Plat LantaiPembersihan Area KerjaRebar workWork item needs review
HuriNaimSubawiToniWahid
Work item needs reviewHuri
Unit A lobi
Rebar workNaim
Unit A lobi
Pembersihan Area KerjaSubawi
Unit A lobi
Cor Plat LantaiToni
Unit A lobi
Work by area
Work area 01 · page 2 of 2Unit A lobi
Standard area
Unit A lobi
1 entry on this page
Cor Plat LantaiWahid
Unit A lobi
Work by area
Work area 02Unit C basement
Standard area
Unit C basement
4 entries on this page
Ground leveling workPembersihan Area KerjaRebar workSkim coat work
HakikPak FarelPranatarizal
Ground leveling workHakik
Unit C basement
Work by area
Work area 03Unit C tangga ujung
Standard area
Unit C tangga ujung
4 entries on this page
Lantai GranitLightweight brick installation
Abdullah BambangFeryWiwin
Lantai GranitAbdullah
Unit C tangga ujung
Work by area
Work area 04Unit A belakang
Standard area
Unit A belakang
3 entries on this page
Work item needs review
FattaPeniWafi
Work item needs reviewFatta
Unit A belakang
Work by area
Work area 05Unit A facade Second Floor
Standard area
Unit A facade Second Floor
2 entries on this page
Skim coat work
MiskatYayan
Skim coat workMiskat
Unit A facade Second Floor
Work by area
Work area 06Unit B facade
Standard area
Unit B facade
2 entries on this page
Plastering work
DulbariRopek
Plastering workDulbari
Unit B facade
Work by area
Work area 07Unit B samping lobi
Standard area
Unit B samping lobi
2 entries on this page
Plastering work
JokoMistun
Plastering workJoko
Unit B samping lobi
Work by area
Work area 08Unit C Room 22
Standard area
Unit C Room 22
2 entries on this page
Lantai Granit
AriHafiz
Lantai GranitAri
Unit C Room 22
Work by area
Work area 09Unit C Room 25
Standard area
Unit C Room 25
2 entries on this page
Lantai Granit
RianSam
Lantai GranitRian
Unit C Room 25
Work by area
Work area 10Unit C Third Floor Gym
Standard area
Unit C Third Floor Gym
2 entries on this page
Plastering work
FarelWaffa
Plastering workFarel
Unit C Third Floor Gym
Work by area
Work area 11Area not filled
Standard area
Area not filled
1 entry on this page
Belanja / Logistik Site
Faisal
Belanja / Logistik SiteFaisal
Area not filled
Work by area
Work area 12Unit A Room 20
Standard area
Unit A Room 20
1 entry on this page
Pembersihan Area Kerja
Rahul
Pembersihan Area KerjaRahul
Unit A Room 20
Work by area
Work area 13Unit A Third Floor
Standard area
Unit A Third Floor
1 entry on this page
Skim coat work
Ridho
Skim coat workRidho
Unit A Third Floor
Work by area
Work area 14Unit A tangga
Standard area
Unit A tangga
1 entry on this page
Chipping work
Rival
Chipping workRival
Unit A tangga
Work by area
Work area 15Unit B
Standard area
Unit B
1 entry on this page
Work item needs review
Yusuf
Work item needs reviewYusuf
Unit B
Work by area
Work area 16Unit B bawah unit
Standard area
Unit B bawah unit
1 entry on this page
Skim coat work
Topik
Skim coat workTopik
Unit B bawah unit
Work by area
Work area 17Unit B Room 17
Standard area
Unit B Room 17
1 entry on this page
Pembersihan Area Kerja
Muhammad
Pembersihan Area KerjaMuhammad
Unit B Room 17
Work by area
Work area 18Unit B Room 27
Standard area
Unit B Room 27
1 entry on this page
Lantai Granit
Adip
Lantai GranitAdip
Unit B Room 27
Work by area
Work area 19Unit B tangga Room 17
Standard area
Unit B tangga Room 17
1 entry on this page
Lantai Granit
Dofir
Lantai GranitDofir
Unit B tangga Room 17
Work by area
Work area 20Unit C Room 14
Standard area
Unit C Room 14
1 entry on this page
Work item needs review
Pawait
Work item needs reviewPawait
Unit C Room 14
Work by area
Work area 21Unit C tangga Room 25
Standard area
Unit C tangga Room 25
1 entry on this page
Lantai Granit
Andri
Lantai GranitAndri
Unit C tangga Room 25
Standard check and completeness
Work item does not match standard naming yet6 entries
The field description does not match project knowledge or BOQ/RAB finance records strongly enough yet.
Area belum diisi1 entry
Lokasi belum ditulis oleh team lapangan.
Area does not meet report standards yet1 entry
The site input does not mention a work area, so it is not used as a final progress conclusion by area.