Daily summary The day's site activity focused on Lantai Granit, Plastering work, and Work item needs review across 28 work areas, supported by Pembersihan Area Kerja, Cor Plat Lantai, and Lightweight brick installation.
Work by area Work area 01 · page 1 of 3 Unit A lobi
Standard area
Unit A lobi 4 entries on this page Concrete casting work Cor Plat Lantai Structural column work Work item needs review
Fatta Fian Naim Peni Syaiful Tohari Wafi Wahid Zaeni Zaini
Concrete casting work Fatta Unit A lobi
Cor Plat Lantai Fian Unit A lobi
Work item needs review Naim Unit A lobi
Cor Plat Lantai Peni Unit A lobi
Work by area Work area 01 · page 2 of 3 Unit A lobi
Standard area
Unit A lobi 4 entries on this page Concrete casting work Syaiful Unit A lobi
Work by area Work area 01 · page 3 of 3 Unit A lobi
Standard area
Unit A lobi 2 entries on this page Cor Plat Lantai Zaeni Unit A lobi
Work by area Work area 02 Unit A belakang
Standard area
Unit A belakang 4 entries on this page Plastering work Skim coat work
Bambang Fendi Miskat Yayan
Plastering work Bambang Unit A belakang
Work by area Work area 03 Unit A Room 20
Standard area
Unit A Room 20 4 entries on this page Pembersihan Area Kerja Plastering work Structural column work
Imron rosidi Muzaki Pawait Rahul
Plastering work Imron rosidi Unit A Room 20
Work by area Work area 04 Unit C Room 24
Standard area
Unit C Room 24 4 entries on this page Lantai Granit Work item needs review
Gani Hoirul Kiki Suarji
Lantai Granit Gani Unit C Room 24
Work by area Work area 05 Building C · Rooftop Floor
Standard area
Building C · Rooftop Floor 3 entries on this page Lantai Granit Skim coat work
Andri Hakik Subairi
Lantai Granit Andri Building C · Rooftop Floor
Work by area Work area 06 Unit B belakang
Standard area
Unit B belakang 3 entries on this page Plastering work Work item needs review
Dul Inol Sikin
Work item needs review Dul Unit B belakang
Work by area Work area 07 Unit B Third Floor
Standard area
Unit B Third Floor 2 entries on this page Lightweight brick installation
Dulbari Ropek
Lightweight brick installation Dulbari Unit B Third Floor
Work by area Work area 08 Unit B rooftop
Standard area
Unit B rooftop 2 entries on this page Lightweight brick installation
Farel Waffa
Lightweight brick installation Farel Unit B rooftop
Work by area Work area 09 Unit B samping lobi
Standard area
Unit B samping lobi 2 entries on this page Plastering work
Joko Mistun
Plastering work Joko Unit B samping lobi
Work by area Work area 10 Unit B tangga Room 17
Standard area
Unit B tangga Room 17 2 entries on this page Lantai Granit
Adip Dofir
Lantai Granit Adip Unit B tangga Room 17
Work by area Work area 11 Unit C basement
Standard area
Unit C basement 2 entries on this page Plastering work
Suraji Yusuf
Plastering work Suraji Unit C basement
Work by area Work area 12 Unit C basement belakang
Standard area
Unit C basement belakang 2 entries on this page Plastering work Skim coat work
Huri Toni
Skim coat work Huri Unit C basement belakang
Work by area Work area 13 Unit C Room 14
Standard area
Unit C Room 14 2 entries on this page Pembersihan Area Kerja Work item needs review
Muhammad Ramli
Pembersihan Area Kerja Muhammad Unit C Room 14
Work by area Work area 14 Unit C Room 21
Standard area
Unit C Room 21 2 entries on this page Lantai Granit
Roni Wiwin
Lantai Granit Roni Unit C Room 21
Work by area Work area 15 Unit C Room 23
Standard area
Unit C Room 23 2 entries on this page Lantai Granit
Ari Hafiz
Lantai Granit Ari Unit C Room 23
Work by area Work area 16 Unit C Room 26
Standard area
Unit C Room 26 2 entries on this page Lantai Granit
Bais Rian
Lantai Granit Bais Unit C Room 26
Work by area Work area 17 Unit C tangga ujung
Standard area
Unit C tangga ujung 2 entries on this page Lantai Granit
Abdullah Sei
Lantai Granit Abdullah Unit C tangga ujung
Work by area Work area 18 Area proyek
Standard area
Area proyek 1 entry on this page Pembersihan Area Kerja
Munir
Pembersihan Area Kerja Munir Area proyek
Work by area Work area 19 Per unit
Standard area
Per unit 1 entry on this page Pembersihan Area Kerja
Pak Farel
Pembersihan Area Kerja Pak Farel Per unit
Work by area Work area 20 Unit A
Standard area
Unit A 1 entry on this page Work item needs review
Pranata
Work item needs review Pranata Unit A
Work by area Work area 21 Unit A facade
Standard area
Unit A facade 1 entry on this page Plastering work
Hosnan
Plastering work Hosnan Unit A facade
Work by area Work area 22 Unit A Third Floor
Standard area
Unit A Third Floor 1 entry on this page Plastering work
Wahyu
Plastering work Wahyu Unit A Third Floor
Work by area Work area 23 Unit B
Standard area
Unit B 1 entry on this page Work item needs review
Ridho
Work item needs review Ridho Unit B
Work by area Work area 24 Unit B facade Third Floor
Standard area
Unit B facade Third Floor 1 entry on this page Plastering work
Parman
Plastering work Parman Unit B facade Third Floor
Work by area Work area 25 Unit B tangga
Standard area
Unit B tangga 1 entry on this page Pembersihan Area Kerja
Subawi
Pembersihan Area Kerja Subawi Unit B tangga
Work by area Work area 26 Unit C kamar Third Floor
Standard area
Unit C kamar Third Floor 1 entry on this page Plastering work
Dani
Plastering work Dani Unit C kamar Third Floor
Work by area Work area 27 Unit C tangga Room 13
Standard area
Unit C tangga Room 13 1 entry on this page Lantai Granit
Redi
Lantai Granit Redi Unit C tangga Room 13
Work by area Work area 28 Unit C tangga Room 23
Standard area
Unit C tangga Room 23 1 entry on this page Lantai Granit
Lobi
Lantai Granit Lobi Unit C tangga Room 23
Standard check and completeness Work item does not match standard naming yet 8 entries The field description does not match project knowledge or BOQ/RAB finance records strongly enough yet.