Daily summary The day's site activity focused on Mason helper, Lantai Granit, and Work item needs review across 37 work areas, supported by Lightweight brick installation, Plastering work, and Structural formwork.
Work by area Work area 01 · page 1 of 2 Besment
Standard area
Besment 4 entries on this page Mason helper Plastering work Rebar work
Soleh Sugik B Suraji Syaiful Yusuf Zaeni
Mason helper Soleh Besment
Plastering work Sugik B Besment
Plastering work Suraji Besment
Rebar work Syaiful Besment
Work by area Work area 01 · page 2 of 2 Besment
Standard area
Besment 2 entries on this page Mason helper Yusuf Besment
Work by area Work area 02 · page 1 of 2 Lobby
Standard area
Lobby 4 entries on this page Lightweight brick installation Structural column work Structural formwork
Affan Joko Kur Sofi Tohari Zaini
Lightweight brick installation Affan Lobby
Work by area Work area 02 · page 2 of 2 Lobby
Standard area
Lobby 2 entries on this page Structural column work Tohari Lobby
Work by area Work area 03 · page 1 of 2 Rostob
Standard area
Rostob 4 entries on this page Lantai Granit Mason helper Skim coat work Work item needs review
Andri Muhammad Mujiono Sam Waffa
Lantai Granit Andri Rostob
Work by area Work area 03 · page 2 of 2 Rostob
Standard area
Rostob 1 entry on this page Work item needs review Waffa Rostob
Work by area Work area 04 Luar proyek
Standard area
Luar proyek 4 entries on this page Work item needs review
Fian Wafi akseh rizal
Work item needs review Fian Luar proyek
Work by area Work area 05 Penthouse Unit B
Standard area
Penthouse Unit B 3 entries on this page Lightweight brick installation Mason helper
Agus Parman Rahul
Mason helper Agus Penthouse Unit B
Work by area Work area 06 Unit A Room 19
Standard area
Unit A Room 19 3 entries on this page Lightweight brick installation Plastering work
Imron rosidi Muzaki Topik
Lightweight brick installation Imron rosidi Unit A Room 19
Work by area Work area 07 Unit C Room 11
Standard area
Unit C Room 11 3 entries on this page Lantai Granit Mason helper Plastering work
Ari Hafiz Sugiantono
Lantai Granit Ari Unit C Room 11
Work by area Work area 08 Unit C penthouse
Standard area
Unit C penthouse 3 entries on this page Lantai Granit Mason helper
Bais Dani Riswan
Lantai Granit Bais Unit C penthouse
Work by area Work area 09 Area not filled
Standard area
Area not filled 2 entries on this page Work item needs review
Adi Feri
Work item needs review Adi Area not filled
Work by area Work area 10 Area luar proyek
Standard area
Area luar proyek 2 entries on this page Plastering work Work item needs review
Fatta Wahyu
Work item needs review Fatta Area luar proyek
Work by area Work area 11 Unit C
Standard area
Unit C 2 entries on this page Lantai Granit Lightweight brick installation
Mustofa Sikin
Lantai Granit Mustofa Unit C
Work by area Work area 12 Unit C Room 14
Standard area
Unit C Room 14 2 entries on this page Work item needs review
Pawait Ramli
Work item needs review Pawait Unit C Room 14
Work by area Work area 13 Unit C Room 21
Standard area
Unit C Room 21 2 entries on this page Lantai Granit Mason helper
Roni Wiwin
Lantai Granit Roni Unit C Room 21
Work by area Work area 14 Unit C Room 24
Standard area
Unit C Room 24 2 entries on this page Lantai Granit Mason helper
Gani Kiki
Lantai Granit Gani Unit C Room 24
Work by area Work area 15 Unit C Room 26
Standard area
Unit C Room 26 2 entries on this page Lantai Granit Mason helper
Anang Dofir
Mason helper Anang Unit C Room 26
Work by area Work area 16 Belakang Unit B tangga
Standard area
Belakang Unit B tangga 1 entry on this page Lightweight brick installation
Wulan
Lightweight brick installation Wulan Belakang Unit B tangga
Work by area Work area 17 Building A · Second Floor
Standard area
Building A · Second Floor 1 entry on this page Plastering work
Ropek
Plastering work Ropek Building A · Second Floor
Work by area Work area 18 in front of Room 13
Standard area
in front of Room 13 1 entry on this page Structural formwork
Pak Ifa
Structural formwork Pak Ifa in front of Room 13
Work by area Work area 19 Depan Unit C Room 12
Standard area
Depan Unit C Room 12 1 entry on this page Structural formwork
Halim
Structural formwork Halim Depan Unit C Room 12
Work by area Work area 20 Keliling proyek
Standard area
Keliling proyek 1 entry on this page Pembersihan Area Kerja
Pak Farel
Pembersihan Area Kerja Pak Farel Keliling proyek
Work by area Work area 21 Penthouse Unit A
Standard area
Penthouse Unit A 1 entry on this page Skim coat work
Fendi
Skim coat work Fendi Penthouse Unit A
Work by area Work area 22 Penthouse Unit C
Standard area
Penthouse Unit C 1 entry on this page Lantai Granit
Abdullah
Lantai Granit Abdullah Penthouse Unit C
Work by area Work area 23 Penthouse Unit C tangga
Standard area
Penthouse Unit C tangga 1 entry on this page Mason helper
Sei
Mason helper Sei Penthouse Unit C tangga
Work by area Work area 24 Rostop luar
Standard area
Rostop luar 1 entry on this page Plastering work
Sugiarto
Plastering work Sugiarto Rostop luar
Work by area Work area 25 tangga Unit B
Standard area
tangga Unit B 1 entry on this page Lantai Granit
Senol
Lantai Granit Senol tangga Unit B
Work by area Work area 26 Tangga Unit B belakang
Standard area
Tangga Unit B belakang 1 entry on this page Mason helper
Naim
Mason helper Naim Tangga Unit B belakang
Work by area Work area 27 Tangga Unit C barat
Standard area
Tangga Unit C barat 1 entry on this page Structural formwork
Dul
Structural formwork Dul Tangga Unit C barat
Work by area Work area 28 Unit A penthouse
Standard area
Unit A penthouse 1 entry on this page Work item needs review
Roy
Work item needs review Roy Unit A penthouse
Work by area Work area 29 Unit B
Standard area
Unit B 1 entry on this page Lantai Granit
Inol
Lantai Granit Inol Unit B
Work by area Work area 30 Unit B Room 27
Standard area
Unit B Room 27 1 entry on this page Ceiling installation work
Suarji
Ceiling installation work Suarji Unit B Room 27
Work by area Work area 31 Unit B rostob
Standard area
Unit B rostob 1 entry on this page Mason helper
Farel
Mason helper Farel Unit B rostob
Work by area Work area 32 Unit C in front of Room 11
Standard area
Unit C in front of Room 11 1 entry on this page Pembersihan Area Kerja
Fauzi
Pembersihan Area Kerja Fauzi Unit C in front of Room 11
Work by area Work area 33 Unit C in front of Room 13
Standard area
Unit C in front of Room 13 1 entry on this page Concrete casting work
Rian
Concrete casting work Rian Unit C in front of Room 13
Work by area Work area 34 Unit C Room 11 tangga
Standard area
Unit C Room 11 tangga 1 entry on this page Lantai Granit
Lobi
Lantai Granit Lobi Unit C Room 11 tangga
Work by area Work area 35 Unit C Room 12
Standard area
Unit C Room 12 1 entry on this page Structural formwork
Hakik
Structural formwork Hakik Unit C Room 12
Work by area Work area 36 Unit C tangga
Standard area
Unit C tangga 1 entry on this page Work item needs review
Ima
Work item needs review Ima Unit C tangga
Work by area Work area 37 Unit C tangga Room 11
Standard area
Unit C tangga Room 11 1 entry on this page Mason helper
Redi
Mason helper Redi Unit C tangga Room 11
Standard check and completeness Work item does not match standard naming yet 12 entries The field description does not match project knowledge or BOQ/RAB finance records strongly enough yet.
Area belum diisi 2 entries Lokasi belum ditulis oleh team lapangan.
Area does not meet report standards yet 2 entries The site input does not mention a work area, so it is not used as a final progress conclusion by area.