Daily summary The day's site activity focused on Work item needs review, Lantai Granit, and Plastering work across 30 work areas, supported by Skim coat work, Pembersihan Area Kerja, and Cor Plat Lantai.
Work by area Work area 01 · page 1 of 2 Unit C basement
Standard area
Unit C basement 4 entries on this page Lightweight brick installation Skim coat work Work item needs review
Muhammad Soleh Sugik B Supriyadi Suraji Yusuf
Work item needs review Muhammad Unit C basement
Skim coat work Soleh Unit C basement
Skim coat work Sugik B Unit C basement
Skim coat work Supriyadi Unit C basement
Work by area Work area 01 · page 2 of 2 Unit C basement
Standard area
Unit C basement 2 entries on this page Lightweight brick installation Suraji Unit C basement
Work by area Work area 02 · page 1 of 2 Unit A Room 19
Standard area
Unit A Room 19 4 entries on this page Plastering work Work item needs review
Fatta Halim Imron rosidi Muzaki Topik
Work item needs review Fatta Unit A Room 19
Work by area Work area 02 · page 2 of 2 Unit A Room 19
Standard area
Unit A Room 19 1 entry on this page Plastering work Topik Unit A Room 19
Work by area Work area 03 · page 1 of 2 Unit A lobi
Standard area
Unit A lobi 4 entries on this page Cor Plat Lantai Work item needs review
Kur Sofi Tohari Wahid Zaini
Work item needs review Kur Unit A lobi
Work by area Work area 03 · page 2 of 2 Unit A lobi
Standard area
Unit A lobi 1 entry on this page Work item needs review Zaini Unit A lobi
Work by area Work area 04 · page 1 of 2 Unit B belakang
Standard area
Unit B belakang 4 entries on this page Plastering work Skim coat work
Al Ima Naim Parman Sugiarto
Plastering work Al Unit B belakang
Work by area Work area 04 · page 2 of 2 Unit B belakang
Standard area
Unit B belakang 1 entry on this page Plastering work Sugiarto Unit B belakang
Work by area Work area 05 Unit C
Standard area
Unit C 4 entries on this page Work item needs review
Fian Ilham Kiki Zaenal
Work item needs review Fian Unit C
Work by area Work area 06 Unit C Room 11
Standard area
Unit C Room 11 4 entries on this page Lantai Granit Pembersihan Area Kerja Work item needs review
Ari Fauzi Hafiz Rian
Lantai Granit Ari Unit C Room 11
Work by area Work area 07 Unit B Room 17
Standard area
Unit B Room 17 3 entries on this page Lantai Granit Work item needs review
Amim Hoirul Senol
Lantai Granit Amim Unit B Room 17
Work by area Work area 08 Unit B Third Floor
Standard area
Unit B Third Floor 3 entries on this page Plastering work Structural column work
Agus Pak Ifa Ropek
Plastering work Agus Unit B Third Floor
Work by area Work area 09 Unit C Room 14
Standard area
Unit C Room 14 3 entries on this page Work item needs review
Pawait Ramli Suarji
Work item needs review Pawait Unit C Room 14
Work by area Work area 10 Unit C Room 25
Standard area
Unit C Room 25 3 entries on this page Lantai Granit
Anang Dofir Mustofa
Lantai Granit Anang Unit C Room 25
Work by area Work area 11 Unit C Third Floor
Standard area
Unit C Third Floor 3 entries on this page Lantai Granit Skim coat work Tile installation
Bais Dani Mujiono
Tile installation Bais Unit C Third Floor
Work by area Work area 12 Building C · Rooftop Floor
Standard area
Building C · Rooftop Floor 2 entries on this page Lantai Granit
Andri Sam
Lantai Granit Andri Building C · Rooftop Floor
Work by area Work area 13 Unit A Room 20
Standard area
Unit A Room 20 2 entries on this page Work item needs review
Affan Joko
Work item needs review Affan Unit A Room 20
Work by area Work area 14 Unit A Third Floor
Standard area
Unit A Third Floor 2 entries on this page Corner bead installation Plastering work
Roy Wahyu
Corner bead installation Roy Unit A Third Floor
Work by area Work area 15 Unit A Third Floor facade
Standard area
Unit A Third Floor facade 2 entries on this page Plastering work
Samsul Sipul
Plastering work Samsul Unit A Third Floor facade
Work by area Work area 16 Unit B belakang Third Floor
Standard area
Unit B belakang Third Floor 2 entries on this page Structural formwork Work item needs review
Dul Sikin
Structural formwork Dul Unit B belakang Third Floor
Work by area Work area 17 Unit B kolam
Standard area
Unit B kolam 2 entries on this page Rebar work
Syaiful Zaeni
Rebar work Syaiful Unit B kolam
Work by area Work area 18 Unit B rooftop
Standard area
Unit B rooftop 2 entries on this page Skim coat work
Farel Waffa
Skim coat work Farel Unit B rooftop
Work by area Work area 19 Unit C Room 12
Standard area
Unit C Room 12 2 entries on this page Lantai Granit
Lobi Redi
Lantai Granit Lobi Unit C Room 12
Work by area Work area 20 Unit C Room 16
Standard area
Unit C Room 16 2 entries on this page Lantai Granit Pembersihan Area Kerja
Gani Munir
Lantai Granit Gani Unit C Room 16
Work by area Work area 21 Unit C Room 21
Standard area
Unit C Room 21 2 entries on this page Lantai Granit
Roni Wiwin
Lantai Granit Roni Unit C Room 21
Work by area Work area 22 Unit C tangga ujung
Standard area
Unit C tangga ujung 2 entries on this page Lantai Granit
Abdullah Sei
Lantai Granit Abdullah Unit C tangga ujung
Work by area Work area 23 Area not filled
Standard area
Area not filled 1 entry on this page Belanja / Logistik Site
Feri
Belanja / Logistik Site Feri Area not filled
Work by area Work area 24 Area proyek per unit
Standard area
Area proyek per unit 1 entry on this page Pembersihan Area Kerja
Pak Farel
Pembersihan Area Kerja Pak Farel Area proyek per unit
Work by area Work area 25 Unit A
Standard area
Unit A 1 entry on this page Work item needs review
Wafi
Work item needs review Wafi Unit A
Work by area Work area 26 Unit A atas tangga Third Floor
Standard area
Unit A atas tangga Third Floor 1 entry on this page Plastering work
Fendi
Plastering work Fendi Unit A atas tangga Third Floor
Work by area Work area 27 Unit B tembok belakang
Standard area
Unit B tembok belakang 1 entry on this page Plastering work
Wulan
Plastering work Wulan Unit B tembok belakang
Work by area Work area 28 Unit C Room 13
Standard area
Unit C Room 13 1 entry on this page Corner bead installation
Sugiantono
Corner bead installation Sugiantono Unit C Room 13
Work by area Work area 29 Unit C ke rooftop
Standard area
Unit C ke rooftop 1 entry on this page Tile installation
Riswan
Tile installation Riswan Unit C ke rooftop
Work by area Work area 30 Unit C kolam ikan
Standard area
Unit C kolam ikan 1 entry on this page Pembersihan Area Kerja
Hakik
Pembersihan Area Kerja Hakik Unit C kolam ikan
Standard check and completeness Work item does not match standard naming yet 18 entries The field description does not match project knowledge or BOQ/RAB finance records strongly enough yet.
Area belum diisi 1 entry Lokasi belum ditulis oleh team lapangan.
Area does not meet report standards yet 1 entry The site input does not mention a work area, so it is not used as a final progress conclusion by area.