Daily summary The day's site activity focused on Lantai Granit, Plastering work, and Concrete casting work across 31 work areas, supported by Work item needs review, Pembersihan Area Kerja, and Structural column work.
Work by area Work area 01 · page 1 of 3 Unit C kolam ikan
Standard area
Unit C kolam ikan 4 entries on this page Concrete casting work
Affan Fatta Fian Hakik Halim Pak Ifa Riswan Ropek Wafi Wahid Zaenal rizal
Concrete casting work Affan Unit C kolam ikan
Concrete casting work Fatta Unit C kolam ikan
Concrete casting work Fian Unit C kolam ikan
Concrete casting work Hakik Unit C kolam ikan
Work by area Work area 01 · page 2 of 3 Unit C kolam ikan
Standard area
Unit C kolam ikan 4 entries on this page Concrete casting work Halim Unit C kolam ikan
Work by area Work area 01 · page 3 of 3 Unit C kolam ikan
Standard area
Unit C kolam ikan 4 entries on this page Concrete casting work Wafi Unit C kolam ikan
Work by area Work area 02 · page 1 of 2 Unit C basement
Standard area
Unit C basement 4 entries on this page Concrete casting work Skim coat work Structural column work
Soleh Sugik B Suraji Yusuf Zaeni
Skim coat work Soleh Unit C basement
Work by area Work area 02 · page 2 of 2 Unit C basement
Standard area
Unit C basement 1 entry on this page Structural column work Zaeni Unit C basement
Work by area Work area 03 Unit A Room 19
Standard area
Unit A Room 19 4 entries on this page Plastering work
Imron rosidi Joko Muzaki Topik
Plastering work Imron rosidi Unit A Room 19
Work by area Work area 04 Unit A Third Floor
Standard area
Unit A Third Floor 4 entries on this page Corner bead installation Plastering work Work item needs review
Fendi Roy Sikin Wahyu
Plastering work Fendi Unit A Third Floor
Work by area Work area 05 Unit A lobi
Standard area
Unit A lobi 3 entries on this page Work item needs review
Kur Tohari Zaini
Work item needs review Kur Unit A lobi
Work by area Work area 06 Unit B Third Floor
Standard area
Unit B Third Floor 3 entries on this page Pembersihan Area Kerja Plastering work Work item needs review
Dul Munir Sugiarto
Work item needs review Dul Unit B Third Floor
Work by area Work area 07 Unit C Room 11
Standard area
Unit C Room 11 3 entries on this page Lantai Granit Pembersihan Area Kerja
Ari Fauzi Hafiz
Lantai Granit Ari Unit C Room 11
Work by area Work area 08 Unit C Room 16
Standard area
Unit C Room 16 3 entries on this page Lantai Granit Pembersihan Area Kerja
Gani Kiki Muhammad
Lantai Granit Gani Unit C Room 16
Work by area Work area 09 Unit C Room 25
Standard area
Unit C Room 25 3 entries on this page Lantai Granit
Anang Dofir Mustofa
Lantai Granit Anang Unit C Room 25
Work by area Work area 10 Area not filled
Standard area
Area not filled 2 entries on this page Belanja / Logistik Site Work item needs review
Adi Feri
Work item needs review Adi Area not filled
Work by area Work area 11 Unit A Room 30
Standard area
Unit A Room 30 2 entries on this page Plastering work
Ramli Sofi
Plastering work Ramli Unit A Room 30
Work by area Work area 12 Unit A Third Floor facade
Standard area
Unit A Third Floor facade 2 entries on this page Lightweight brick installation
Samsul Sipul
Lightweight brick installation Samsul Unit A Third Floor facade
Work by area Work area 13 Unit B Room 17
Standard area
Unit B Room 17 2 entries on this page Lantai Granit Work item needs review
Amim Hoirul
Lantai Granit Amim Unit B Room 17
Work by area Work area 14 Unit B rooftop
Standard area
Unit B rooftop 2 entries on this page Plastering work
Farel Waffa
Plastering work Farel Unit B rooftop
Work by area Work area 15 Unit B tangga belakang
Standard area
Unit B tangga belakang 2 entries on this page Plastering work
Naim Wulan
Plastering work Naim Unit B tangga belakang
Work by area Work area 16 Unit C Room 12
Standard area
Unit C Room 12 2 entries on this page Lantai Granit
Lobi Redi
Lantai Granit Lobi Unit C Room 12
Work by area Work area 17 Unit C Room 14
Standard area
Unit C Room 14 2 entries on this page Work item needs review
Pawait Suarji
Work item needs review Pawait Unit C Room 14
Work by area Work area 18 Unit C Room 21
Standard area
Unit C Room 21 2 entries on this page Lantai Granit
Roni Wiwin
Lantai Granit Roni Unit C Room 21
Work by area Work area 19 Unit C Room 24
Standard area
Unit C Room 24 2 entries on this page Plastering work
Dani Sugiantono
Plastering work Dani Unit C Room 24
Work by area Work area 20 Building C · Rooftop Floor
Standard area
Building C · Rooftop Floor 1 entry on this page Lantai Granit
Andri
Lantai Granit Andri Building C · Rooftop Floor
Work by area Work area 21 Unit B belakang
Standard area
Unit B belakang 1 entry on this page Plastering work
Sam
Plastering work Sam Unit B belakang
Work by area Work area 22 Unit B Room 28
Standard area
Unit B Room 28 1 entry on this page Lantai Granit
Bais
Lantai Granit Bais Unit B Room 28
Work by area Work area 23 Unit B Second Floor
Standard area
Unit B Second Floor 1 entry on this page Plastering work
Parman
Plastering work Parman Unit B Second Floor
Work by area Work area 24 Unit B tangga Room 17
Standard area
Unit B tangga Room 17 1 entry on this page Lantai Granit
Senol
Lantai Granit Senol Unit B tangga Room 17
Work by area Work area 25 Unit C area proyek
Standard area
Unit C area proyek 1 entry on this page Pembersihan Area Kerja
Pak Farel
Pembersihan Area Kerja Pak Farel Unit C area proyek
Work by area Work area 26 Unit C di basement
Standard area
Unit C di basement 1 entry on this page Structural column work
Syaiful
Structural column work Syaiful Unit C di basement
Work by area Work area 27 Unit C Room 26
Standard area
Unit C Room 26 1 entry on this page Pembersihan Area Kerja
Rian
Pembersihan Area Kerja Rian Unit C Room 26
Work by area Work area 28 Unit C kolam ikan/molen
Standard area
Unit C kolam ikan/molen 1 entry on this page Concrete casting work
Ilham
Concrete casting work Ilham Unit C kolam ikan/molen
Work by area Work area 29 Unit C Third Floor
Standard area
Unit C Third Floor 1 entry on this page Skim coat work
Mujiono
Skim coat work Mujiono Unit C Third Floor
Work by area Work area 30 Unit C tangga ujung
Standard area
Unit C tangga ujung 1 entry on this page Lantai Granit
Sei
Lantai Granit Sei Unit C tangga ujung
Work by area Work area 31 Unit C tangga ujung Third Floor
Standard area
Unit C tangga ujung Third Floor 1 entry on this page Lantai Granit
Abdullah
Lantai Granit Abdullah Unit C tangga ujung Third Floor
Standard check and completeness Work item does not match standard naming yet 9 entries The field description does not match project knowledge or BOQ/RAB finance records strongly enough yet.
Area belum diisi 2 entries Lokasi belum ditulis oleh team lapangan.
Area does not meet report standards yet 2 entries The site input does not mention a work area, so it is not used as a final progress conclusion by area.