Daily summary The day's site activity focused on Plastering work, Lantai Granit, and Work item needs review across 27 work areas, supported by Lightweight brick installation, Pembersihan Area Kerja, and Rebar work.
Work by area Work area 01 · page 1 of 2 Unit C Third Floor
Standard area
Unit C Third Floor 4 entries on this page Lantai Granit Skim coat work
Andri Bais Mujiono Riswan Sam
Lantai Granit Andri Unit C Third Floor
Lantai Granit Bais Unit C Third Floor
Skim coat work Mujiono Unit C Third Floor
Skim coat work Riswan Unit C Third Floor
Work by area Work area 01 · page 2 of 2 Unit C Third Floor
Standard area
Unit C Third Floor 1 entry on this page Lantai Granit Sam Unit C Third Floor
Work by area Work area 02 Unit A Room 19
Standard area
Unit A Room 19 4 entries on this page Plastering work
Imron rosidi Muzaki Pawait Topik
Plastering work Imron rosidi Unit A Room 19
Work by area Work area 03 Unit A lobi
Standard area
Unit A lobi 4 entries on this page Work item needs review
Halim Tohari Wahid Zaini
Work item needs review Halim Unit A lobi
Work by area Work area 04 Unit B Third Floor
Standard area
Unit B Third Floor 4 entries on this page Plastering work Structural column work Work item needs review
Agus Huri Joko Pak Ifa
Plastering work Agus Unit B Third Floor
Work by area Work area 05 Unit C basement
Standard area
Unit C basement 4 entries on this page Concrete casting work Plastering work Rebar work
Soleh Suraji Syaiful Yusuf
Concrete casting work Soleh Unit C basement
Work by area Work area 06 Unit C Room 25
Standard area
Unit C Room 25 4 entries on this page Lantai Granit
Anang Dofir Munir Mustofa
Lantai Granit Anang Unit C Room 25
Work by area Work area 07 Unit B belakang
Standard area
Unit B belakang 3 entries on this page Plastering work
Al Parman Sugiarto
Plastering work Al Unit B belakang
Work by area Work area 08 Unit C Room 11
Standard area
Unit C Room 11 3 entries on this page Lantai Granit Pembersihan Area Kerja
Ari Fauzi Hafiz
Lantai Granit Ari Unit C Room 11
Work by area Work area 09 Unit C Room 16
Standard area
Unit C Room 16 3 entries on this page Lantai Granit Pembersihan Area Kerja
Gani Kiki Muhammad
Lantai Granit Gani Unit C Room 16
Work by area Work area 10 Area not filled
Standard area
Area not filled 2 entries on this page Belanja / Logistik Site Work item needs review
Adi Feri
Work item needs review Adi Area not filled
Work by area Work area 11 Unit A Room 30
Standard area
Unit A Room 30 2 entries on this page Plastering work
Ramli Sofi
Plastering work Ramli Unit A Room 30
Work by area Work area 12 Unit A Third Floor
Standard area
Unit A Third Floor 2 entries on this page Corner bead installation Plastering work
Fendi Hakik
Plastering work Fendi Unit A Third Floor
Work by area Work area 13 Unit A samping
Standard area
Unit A samping 2 entries on this page Plastering work
Dul Sikin
Plastering work Dul Unit A samping
Work by area Work area 14 Unit B rooftop
Standard area
Unit B rooftop 2 entries on this page Plastering work
Farel Waffa
Plastering work Farel Unit B rooftop
Work by area Work area 15 Unit B tangga
Standard area
Unit B tangga 2 entries on this page Lightweight brick installation Plastering work
Naim Wulan
Lightweight brick installation Naim Unit B tangga
Work by area Work area 16 Unit C
Standard area
Unit C 2 entries on this page Lightweight brick installation Rebar work
Pak Farel Zaeni
Lightweight brick installation Pak Farel Unit C
Work by area Work area 17 Unit C Room 12
Standard area
Unit C Room 12 2 entries on this page Lightweight brick installation
Ilham Ropek
Lightweight brick installation Ilham Unit C Room 12
Work by area Work area 18 Unit C Room 21
Standard area
Unit C Room 21 2 entries on this page Lantai Granit
Roni Wiwin
Lantai Granit Roni Unit C Room 21
Work by area Work area 19 Unit C Room 22
Standard area
Unit C Room 22 2 entries on this page Lantai Granit
Abdullah Sei
Lantai Granit Abdullah Unit C Room 22
Work by area Work area 20 Unit A Room 29
Standard area
Unit A Room 29 1 entry on this page Work item needs review
Kur
Work item needs review Kur Unit A Room 29
Work by area Work area 21 Unit A Third Floor atas tangga
Standard area
Unit A Third Floor atas tangga 1 entry on this page Plastering work
Wahyu
Plastering work Wahyu Unit A Third Floor atas tangga
Work by area Work area 22 Unit B Room 17
Standard area
Unit B Room 17 1 entry on this page Work item needs review
Hoirul
Work item needs review Hoirul Unit B Room 17
Work by area Work area 23 Unit B Room 28
Standard area
Unit B Room 28 1 entry on this page Lantai Granit
Dani
Lantai Granit Dani Unit B Room 28
Work by area Work area 24 Unit B kamar mandi Third Floor
Standard area
Unit B kamar mandi Third Floor 1 entry on this page Work item needs review
akseh
Work item needs review akseh Unit B kamar mandi Third Floor
Work by area Work area 25 Unit C Room 13
Standard area
Unit C Room 13 1 entry on this page Work item needs review
Sugiantono
Work item needs review Sugiantono Unit C Room 13
Work by area Work area 26 Unit C Room 14
Standard area
Unit C Room 14 1 entry on this page Work item needs review
Affan
Work item needs review Affan Unit C Room 14
Work by area Work area 27 Unit C Room 15
Standard area
Unit C Room 15 1 entry on this page Work item needs review
Suarji
Work item needs review Suarji Unit C Room 15
Standard check and completeness Work item does not match standard naming yet 13 entries The field description does not match project knowledge or BOQ/RAB finance records strongly enough yet.
Area belum diisi 2 entries Lokasi belum ditulis oleh team lapangan.
Area does not meet report standards yet 2 entries The site input does not mention a work area, so it is not used as a final progress conclusion by area.