The day's site activity focused on Concrete casting work, Lantai Granit, and Skim coat work across 30 work areas, supported by Work item needs review, Pembersihan Area Kerja, and Rebar work.
Work by area
Work area 01 · page 1 of 3Unit B facade
Standard area
Unit B facade
4 entries on this page
Concrete casting work
AgusAnangAwangHarIlhamPeniWafiZaenalakseh
Concrete casting workAgus
Unit B facade
Concrete casting workAnang
Unit B facade
Concrete casting workAwang
Unit B facade
Concrete casting workHar
Unit B facade
Work by area
Work area 01 · page 2 of 3Unit B facade
Standard area
Unit B facade
4 entries on this page
Concrete casting workIlham
Unit B facade
Work by area
Work area 01 · page 3 of 3Unit B facade
Standard area
Unit B facade
1 entry on this page
Concrete casting workakseh
Unit B facade
Work by area
Work area 02 · page 1 of 2Unit B Fourth Floor facade
Standard area
Unit B Fourth Floor facade
4 entries on this page
Concrete casting work
AstroFattaHalimIfanPak IfaParlanWahid
Concrete casting workAstro
Unit B Fourth Floor facade
Work by area
Work area 02 · page 2 of 2Unit B Fourth Floor facade
Standard area
Unit B Fourth Floor facade
3 entries on this page
Concrete casting workPak Ifa
Unit B Fourth Floor facade
Work by area
Work area 03Unit C in front of Room 11
Standard area
Unit C in front of Room 11
4 entries on this page
Rebar work
Sugiarto SyaifulTopikrizal
Rebar workSugiarto
Unit C in front of Room 11
Work by area
Work area 04Unit C Room 11
Standard area
Unit C Room 11
4 entries on this page
Corner bead installationPembersihan Area Kerja
FauziHoirulRianSuarji
Pembersihan Area KerjaFauzi
Unit C Room 11
Work by area
Work area 05Unit C Room 12
Standard area
Unit C Room 12
4 entries on this page
Lantai GranitPembersihan Area Kerja
LobiMuhammadRahurRedi
Lantai GranitLobi
Unit C Room 12
Work by area
Work area 06Unit C Room 23
Standard area
Unit C Room 23
4 entries on this page
Lantai GranitPlastering work
AlAriImron rosidiMuzaki
Lantai GranitAl
Unit C Room 23
Work by area
Work area 07Unit C Third Floor
Standard area
Unit C Third Floor
4 entries on this page
Lantai GranitSkim coat work
AndriMujionoRiswanSam
Lantai GranitAndri
Unit C Third Floor
Work by area
Work area 08Unit A belakang Third Floor
Standard area
Unit A belakang Third Floor
3 entries on this page
Lightweight brick installationPembersihan Area Kerja
DulFendi Wahyu
Pembersihan Area KerjaDul
Unit A belakang Third Floor
Work by area
Work area 09Unit C basement
Standard area
Unit C basement
3 entries on this page
Skim coat work
SupriyadiSurajiYusuf
Skim coat workSupriyadi
Unit C basement
Work by area
Work area 10Unit C Room 16
Standard area
Unit C Room 16
3 entries on this page
Lantai GranitWork item needs review
GaniKikiSugiantono
Lantai GranitGani
Unit C Room 16
Work by area
Work area 11Unit C tangga ujung
Standard area
Unit C tangga ujung
3 entries on this page
Corner bead installationSkim coat work
ImaSolehSugik B
Corner bead installationIma
Unit C tangga ujung
Work by area
Work area 12Area not filled
Standard area
Area not filled
2 entries on this page
Belanja / Logistik SiteWork item needs review
AdiFeri
Work item needs reviewAdi
Area not filled
Work by area
Work area 13Basement
Standard area
Basement
2 entries on this page
Work item needs review
HuriTormudi
Work item needs reviewHuri
Basement
Work by area
Work area 14Unit A in front of Room 19
Standard area
Unit A in front of Room 19
2 entries on this page
Skim coat work
FarelRoy
Skim coat workFarel
Unit A in front of Room 19
Work by area
Work area 15Unit A lobi
Standard area
Unit A lobi
2 entries on this page
Rebar work
TohariZaini
Rebar workTohari
Unit A lobi
Work by area
Work area 16Unit B belakang
Standard area
Unit B belakang
2 entries on this page
Structural column workWork item needs review
NaimWulan
Work item needs reviewNaim
Unit B belakang
Work by area
Work area 17Unit B Room 17
Standard area
Unit B Room 17
2 entries on this page
Work item needs review
BaisDani
Work item needs reviewBais
Unit B Room 17
Work by area
Work area 18Unit C Room 13
Standard area
Unit C Room 13
2 entries on this page
Lantai Granit
RoniWiwin
Lantai GranitRoni
Unit C Room 13
Work by area
Work area 19Unit C Room 24
Standard area
Unit C Room 24
2 entries on this page
Lantai Granit
Abdullah Sei
Lantai GranitAbdullah
Unit C Room 24
Work by area
Work area 20Unit C Room 25
Standard area
Unit C Room 25
2 entries on this page
Lantai Granit
DofirHasan
Lantai GranitDofir
Unit C Room 25
Work by area
Work area 21Unit C Room 26
Standard area
Unit C Room 26
2 entries on this page
Plastering work
HakikPawait
Plastering workHakik
Unit C Room 26
Work by area
Work area 22Area proyek per unit
Standard area
Area proyek per unit
1 entry on this page
Pembersihan Area Kerja
Pak Farel
Pembersihan Area KerjaPak Farel
Area proyek per unit
Work by area
Work area 23Unit A Third Floor
Standard area
Unit A Third Floor
1 entry on this page
Pembersihan Area Kerja
Sikin
Pembersihan Area KerjaSikin
Unit A Third Floor
Work by area
Work area 24Unit A Third Floor belakang
Standard area
Unit A Third Floor belakang
1 entry on this page
Plastering work
Sodik
Plastering workSodik
Unit A Third Floor belakang
No photo evidence for this entry yet.
Work by area
Work area 25Unit B Room 18
Standard area
Unit B Room 18
1 entry on this page
Plastering work
Sofi
Plastering workSofi
Unit B Room 18
Work by area
Work area 26Unit C
Standard area
Unit C
1 entry on this page
Pembersihan Area Kerja
Munir
Pembersihan Area KerjaMunir
Unit C
Work by area
Work area 27Unit C dikamar 14
Standard area
Unit C dikamar 14
1 entry on this page
Work item needs review
Mistun
Work item needs reviewMistun
Unit C dikamar 14
Work by area
Work area 28Unut A lobi
Standard area
Unut A lobi
1 entry on this page
Rebar work
Kur
Rebar workKur
Unut A lobi
Work by area
Work area 29Unut C dikamar 11
Standard area
Unut C dikamar 11
1 entry on this page
Work item needs review
Zaeni
Work item needs reviewZaeni
Unut C dikamar 11
Work by area
Work area 30UUnit B facade
Standard area
UUnit B facade
1 entry on this page
Concrete casting work
Fian
Concrete casting workFian
UUnit B facade
Standard check and completeness
Work item does not match standard naming yet9 entries
The field description does not match project knowledge or BOQ/RAB finance records strongly enough yet.
Photo evidence missing3 entries
The entry can still be read as a site report, but the visual evidence is incomplete.
Area belum diisi2 entries
Lokasi belum ditulis oleh team lapangan.
Area does not meet report standards yet2 entries
The site input does not mention a work area, so it is not used as a final progress conclusion by area.