Daily summary The day's site activity focused on Lantai Granit, Work item needs review, and Plastering work across 37 work areas, supported by Lightweight brick installation, Structural column work, and Skim coat work.
Work by area Work area 01 · page 1 of 2 Unit B belakang
Standard area
Unit B belakang 4 entries on this page Skim coat work Structural column work Structural formwork
Huri Naim Pak Ifa Sikin Wulan akseh
Structural formwork Huri Unit B belakang
Structural column work Naim Unit B belakang
Skim coat work Pak Ifa Unit B belakang
Structural column work Sikin Unit B belakang
Work by area Work area 01 · page 2 of 2 Unit B belakang
Standard area
Unit B belakang 2 entries on this page Structural column work Wulan Unit B belakang
Work by area Work area 02 · page 1 of 2 Unit A
Standard area
Unit A 4 entries on this page Lightweight brick installation Pembersihan Area Kerja Structural column work
Fian Peni Ramdan Tohari Zaini
Lightweight brick installation Fian Unit A
Work by area Work area 02 · page 2 of 2 Unit A
Standard area
Unit A 1 entry on this page Structural column work Zaini Unit A
Work by area Work area 03 Unit A belakang
Standard area
Unit A belakang 4 entries on this page Plastering work Work item needs review
Awang Fendi Wafi Wahyu
Work item needs review Awang Unit A belakang
Work by area Work area 04 Unit C basement
Standard area
Unit C basement 4 entries on this page Rebar work Skim coat work Work item needs review
Muzaki Suraji Yusuf Zaeni
Work item needs review Muzaki Unit C basement
Work by area Work area 05 Unit C Room 13
Standard area
Unit C Room 13 4 entries on this page Lantai Granit Plastering work
Bais Hakik Roni Wiwin
Plastering work Bais Unit C Room 13
Work by area Work area 06 Lobby
Standard area
Lobby 3 entries on this page Mason helper Structural formwork
Anang Fatta Kur
Mason helper Anang Lobby
Work by area Work area 07 Unit B Third Floor
Standard area
Unit B Third Floor 3 entries on this page Structural column work Work item needs review
Astro Parlan Wahid
Structural column work Astro Unit B Third Floor
Work by area Work area 08 Unit C Room 25
Standard area
Unit C Room 25 3 entries on this page Lantai Granit Mason helper
Dofir Hasan Sei
Lantai Granit Dofir Unit C Room 25
Work by area Work area 09 Area not filled
Standard area
Area not filled 2 entries on this page Belanja / Logistik Site Work item needs review
Adi Feri
Work item needs review Adi Area not filled
Work by area Work area 10 Depan pagar dekat kolam
Standard area
Depan pagar dekat kolam 2 entries on this page Lightweight brick installation
Pawait Sugiarto
Lightweight brick installation Pawait Depan pagar dekat kolam
Work by area Work area 11 Unit A First Floor
Standard area
Unit A First Floor 2 entries on this page Plastering work
Al Halim
Plastering work Al Unit A First Floor
Work by area Work area 12 Unit C Room 14
Standard area
Unit C Room 14 2 entries on this page Lantai Granit
Lobi Redi
Lantai Granit Lobi Unit C Room 14
Work by area Work area 13 Unit C Room 15
Standard area
Unit C Room 15 2 entries on this page Lantai Granit
Gani Kiki
Lantai Granit Gani Unit C Room 15
Work by area Work area 14 Unit C Room 21
Standard area
Unit C Room 21 2 entries on this page Lightweight brick installation
Imron rosidi Ropek
Lightweight brick installation Imron rosidi Unit C Room 21
Work by area Work area 15 Unit C outdoor area
Standard area
Unit C outdoor area 2 entries on this page Lantai Granit
Andri Sam
Lantai Granit Andri Unit C outdoor area
Work by area Work area 16 Unit C tangga ujung basement
Standard area
Unit C tangga ujung basement 2 entries on this page Plastering work
Soleh Sugik B
Plastering work Soleh Unit C tangga ujung basement
Work by area Work area 17 Area semua proyek
Standard area
Area semua proyek 1 entry on this page Pembersihan Area Kerja
Pak Farel
Pembersihan Area Kerja Pak Farel Area semua proyek
Work by area Work area 18 Building A · Room 30 · First Floor
Standard area
Building A · Room 30 · First Floor 1 entry on this page Plastering work
Roy
Plastering work Roy Building A · Room 30 · First Floor
Work by area Work area 19 in front of Room 13
Standard area
in front of Room 13 1 entry on this page Rebar work
Syaiful
Rebar work Syaiful in front of Room 13
Work by area Work area 20 in front of Room 20 Unit A
Standard area
in front of Room 20 Unit A 1 entry on this page Mason helper
Farel
Mason helper Farel in front of Room 20 Unit A
Work by area Work area 21 Depan pager dekat kolam
Standard area
Depan pager dekat kolam 1 entry on this page Lightweight brick installation
Topik
Lightweight brick installation Topik Depan pager dekat kolam
Work by area Work area 22 Init A
Standard area
Init A 1 entry on this page Lightweight brick installation
Zaenal
Lightweight brick installation Zaenal Init A
Work by area Work area 23 Room 16 Unit C
Standard area
Room 16 Unit C 1 entry on this page Work item needs review
Rahur
Work item needs review Rahur Room 16 Unit C
Work by area Work area 24 Luar proyek
Standard area
Luar proyek 1 entry on this page Material Handling / Angkut Material
Solikin
Material Handling / Angkut Material Solikin Luar proyek
Work by area Work area 25 Unit A bawah tangga
Standard area
Unit A bawah tangga 1 entry on this page Plastering work
Sofi
Plastering work Sofi Unit A bawah tangga
Work by area Work area 26 Unit B behind Room 18
Standard area
Unit B behind Room 18 1 entry on this page Corner bead installation
Ima
Corner bead installation Ima Unit B behind Room 18
Work by area Work area 27 Unit B Room 17
Standard area
Unit B Room 17 1 entry on this page Work item needs review
Dani
Work item needs review Dani Unit B Room 17
Work by area Work area 28 Unit B Room 28
Standard area
Unit B Room 28 1 entry on this page Work item needs review
Tormudi
Work item needs review Tormudi Unit B Room 28
Work by area Work area 29 Unit B ke Third Floor
Standard area
Unit B ke Third Floor 1 entry on this page Work item needs review
Ifan
Work item needs review Ifan Unit B ke Third Floor
Work by area Work area 30 Unit C
Standard area
Unit C 1 entry on this page Lantai Granit
Dul
Lantai Granit Dul Unit C
Work by area Work area 31 Unit C di Room 11
Standard area
Unit C di Room 11 1 entry on this page Rebar work
rizal
Rebar work rizal Unit C di Room 11
Work by area Work area 32 Unit C dikamar 14
Standard area
Unit C dikamar 14 1 entry on this page Work item needs review
Mistun
Work item needs review Mistun Unit C dikamar 14
Work by area Work area 33 Unit C Room 22
Standard area
Unit C Room 22 1 entry on this page Work item needs review
Sugiantono
Work item needs review Sugiantono Unit C Room 22
Work by area Work area 34 Unit C Room 24
Standard area
Unit C Room 24 1 entry on this page Lantai Granit
Abdullah
Lantai Granit Abdullah Unit C Room 24
Work by area Work area 35 Unit C tangga ujung
Standard area
Unit C tangga ujung 1 entry on this page Skim coat work
Mujiono
Skim coat work Mujiono Unit C tangga ujung
Work by area Work area 36 Unit C ujung
Standard area
Unit C ujung 1 entry on this page Skim coat work
Riswan
Skim coat work Riswan Unit C ujung
Work by area Work area 37 Unut A
Standard area
Unut A 1 entry on this page Pembersihan Area Kerja
Ilham
Pembersihan Area Kerja Ilham Unut A
Standard check and completeness Work item does not match standard naming yet 11 entries The field description does not match project knowledge or BOQ/RAB finance records strongly enough yet.
Area belum diisi 2 entries Lokasi belum ditulis oleh team lapangan.
Area does not meet report standards yet 2 entries The site input does not mention a work area, so it is not used as a final progress conclusion by area.
Photo evidence missing 1 entry The entry can still be read as a site report, but the visual evidence is incomplete.